I-96/Pleasant Valley Bridge Repair To Be Completed By Labor Day
Crews are working to replace an overpass that has been missing for about nine months on I-96.
It was damaged beyond repair last September, when a machinery delivery truck crashed into it.
Engineers say they will be filling the open space with "800-thousand pounds of concrete and steel."
Officials from MDOT say they expect for the bridge to be complete and open to traffic by Labor Day.
The project is expected to cost around $1.6M
MDOT says it will seek reimbursement from the company that owns the truck that took it down. (WILX)
Crews working to replace overpass
Crews are working to replace an overpass that has been missing for about nine months on I-96. It was damaged beyond repair last September, when a machinery delivery truck crashed into it. Engineers say they will be filling the open space with "800-thousand pounds of concrete and steel."
An update from MDOT from yesterday says the overall completion date will be NOVEMBER of 2018 and the estimated cost will be $2.1 Million.
MDOT - Westbound I-96 closed for bridge work near Brighton overnight Monday into early Tuesday